ITEM | RUBRO | U. M. | Cantidad |
1 | TRABAJOS PREVIOS | ||
1.1 | Limpieza de terreno | m2 | 6.216,00 |
1.2 | Replanteo y Medicion | m2 | 2.970,00 |
1.3 | Obrador | gl. | 1,00 |
1.4 | Istalaciones provisorias, baños temporales para personal | gl. | 1,00 |
2 | HORMIGON ARMADO | ||
2.1 | Pilotes de hormigon armado de ø 40 - Fck 210 | ml | 11,00 |
2.2 | Pilotes de hormigon armado de ø 50 - Fck 210 | ml | 11,00 |
2.3 | Pilotes de hormigon armado de ø 60 - Fck 210 | ml | 11,00 |
2.4 | Cabezal de hormigon armado - Fck 250 | m3 | 64,00 |
2.5 | Vigas de Fundacion - Fck 250 | m3 | 99,50 |
2.6 | Pilares - Fck 250 | m3 | 159,00 |
2.7 | Vigas Planta alta - Fck 250 | m3 | 135,00 |
2.8 | Vigas Planta Graderia - Fck 250 | m3 | 173,00 |
2.9 | Vigas Planta Cabina de perioristas - Fck 250 | m3 | 37,00 |
2.10 | Vigas Planta techo - Fck 250 | m3 | 28,21 |
2.11 | Losa cabina de periodistas - Fck 250 | m3 | 9,90 |
2.12 | Losa planta alta - Fck 250 | m3 | 208,00 |
2.13 | Graderias - Fck 250 | m3 | 416,00 |
2.14 | Escalera tipo 1 - Fck 250 | m3 | 4,00 |
2.15 | Escalera tipo 2 - Fck 250 | m3 | 2,00 |
2.16 | Escalera tipo 3 - Fck 250 | m3 | 2,10 |
2.17 | Escalera tipo 4 - Fck 250 | m3 | 2,50 |
3 | MAMPOSTERIAS | ||
3.1 | Mampostería de ladrillo comun de 0,15 m, Sector vestuarios | m2 | 310,00 |
3.2 | Mampostería de ladrillo comun de 0,15 m, Sector Oficinas Depositos | m2 | 219,12 |
3.3 | Mampostería de ladrillo comun de 0,15 m, Sector bajo graderias | m2 | 372,90 |
3.4 | Mampostería de ladrillo comun de 0,15 m, Sector Oficinas Aulas | m2 | 268,95 |
3.5 | Mampostería de ladrillo comun de 0,15 m, Sector Salon Multiuso | m2 | 567,60 |
3.6 | Mampostería de ladrillo comun de 0,15 m, Nivel Graderias | m2 | 237,00 |
3.7 | Muros en 4 Fachadas. Mampostería de ladrillo comun de 0,15 m, con vanos según diseño |
m2 | 2.098,00 |
4 | ENVARILLADO | ||
4.1 | De mamposteria en aberturas | ml | 114,00 |
5 | REVOQUES | ||
5.1 | De paredes interiores | m2 | 620,00 |
5.2 | De paredes Exteriores con hidrofugo | m2 | 2.091,60 |
5.3 | De pilares | ml | 371,84 |
5.4 | De base de azulejos - Azotada Impermeable | m2 | 403,20 |
5.5 | De cielorrasos y Graderias | m2 | 6.565,00 |
6 | AISLACIONES | ||
6.1 | Aislación de losas de baños | m2 | 14,52 |
6.2 | Horizontal de mamposteria | ml | 320,00 |
7 | TECHO METALICO | ||
7.1 | Insertos Metalicos | gl. | 28,00 |
7.2 | Estructura metalica de cobertura, incluye: cabriadas reticuladas fabricadas con perfiles doble angulos de 4´´x1/4´´ y angulos de 2´´x1/8´´ y 1.1/2´´x1/8´´ laminados en caliente. Correas de perfiles C140x2,00 mm. Vigas riostras en perfiles 2C140x2,00 mm. Tensores de varillas lisas de 12 y 16 mm. Pintura de estructuras con antioxido y esmalte sintetico color blanco. | un. | 2.980,00 |
7.3 | Provision y montaje de chapa Panel para techo,termoacustico PIR 30mm, trapezio superior y liso inferior color blanco en ambas caras.Tapa cumbrera en chapa galvanizada Nro. 26. Plegado de terminaciones en extremos de techo | m2 | 2.980,00 |
8 | CONTRAPISOS Y PISOS | ||
8.1 | Contrapiso sobre terreno natural (h=10cm) | m2 | 672,00 |
8.2 | Contrapiso sobre losa (h=8cm) | m2 | 185,00 |
8.3 | Carpeta para colocacion de piso | m2 | 857,00 |
8.4 | Piso de cancha interior,entorno de cancha y canchas exteriores (Hormigón con terminación Pavicron) esp. 10cm | m2 | 2.581,00 |
8.5 | Piso en Salon Multiuso, acceso publico,pasillos, (Hormigón con terminación llaneado helicoptero) | m2 | 874,00 |
8.6 | Piso en Aulas, oficinas y deposito (Cerámica Esmaltada) (Hasta 40.000 xm2) | m2 | 280,00 |
8.7 | Piso en vestuarios, baños, area Vip y cabina de prensa (Cerámica Esmaltada) (Hasta 65.000 xm2) | m2 | 247,00 |
8.8 | Piso en escalera y Graderias (Alisada de Cemento) | m2 | 69,37 |
8.9 | Provisión y colocación de piso vinilico inspire Havanna OAK 967M (danza) | m2 | 62,00 |
8.10 | Provisión y colocación de GOMA CON FELPA - MONEDA 1.40 DE ANCHO (gimnacio) | m2 | 85,00 |
9 | Vereda y camineros | - | |
9.1 | Contrapiso sobre terreno natural (h=10cm) | m2 | 1.152,00 |
9.2 | Piso Exterior (Baldosones de Hormigón) | m2 | 1.152,00 |
10 | REVESTIDOS | ||
10.1 | Azulejos en baños y vestuarios (Hasta 40.000 xm2) | m2 | 403,20 |
11 | INSTALACIÓN SANITARIA Y PCI | ||
11.1 | PROVISION Y COLOCACIÓN DE TUBO POLIPROPILENO TERMOFUSION PN 20 DN (75mm) | ml | 44,10 |
11.2 | PROVISION Y COLOCACIÓN DE TUBO POLIPROPILENO TERMOFUSION PN 20 DN (63mm) | ml | 122,85 |
11.3 | PROVISION Y COLOCACIÓN DE TUBO POLIPROPILENO TERMOFUSION PN 20 DN (50mm) | ml | 91,35 |
11.4 | PROVISION Y COLOCACIÓN DE TUBO POLIPROPILENO TERMOFUSION PN 20 DN (32mm) | ml | 152,25 |
11.5 | PROVISION Y COLOCACIÓN DE TUBO POLIPROPILENO TERMOFUSION PN 20 DN (25mm) | ml | 236,15 |
11.6 | PROVISION Y COLOCACIÓN DE TUBO POLIPROPILENO TERMOFUSION PN 20 DN (20mm) | ml | 30,01 |
11.7 | Conexión fusion con todos los accesorios puesta en funsionamiento | un. | 82,00 |
11.8 | PROVISION Y COLOCACION DE LLAVE EXCLUSA CROMADA DN (1 1/2") | un. | 32,00 |
11.9 | PROVISION Y COLOCACION DE VALVULA DE DESCARGA DN (1 1/2") | un. | 30,00 |
11.10 | PROVISION Y COLOCACION DE CANILLA DE PATIO DN (3/4") Con accesorios | un. | 3,00 |
11.11 | PROVISION Y COLOCACION DE Medidor DN (1") Con accesorios y caja de medidor | un. | 1,00 |
11.12 | PROVISION Y COLOCACION DE TERMOCALEFON VERTICAL Cap.= 40 Lts. | un. | 2,00 |
11.13 | PROVISION Y COLOCACION DE TERMOCALEFON VERTICAL Cap.= 50 Lts. | un. | 4,00 |
11.14 | PROVISION Y COLOCACION DE TERMOCALEFON VERTICAL Cap.= 100 Lts. | un. | 4,00 |
11.15 | PROVISION Y COLOCACION DE TANQUE TIPO COPA. Cap.= 50.000 Lts. | gl. | 1,00 |
11.16 | PROVISIÓN Y COLOCACIÓN DE VALVULA ESFERICA DN (2") PARA TANQUE TIPO COPA | un. | 1,00 |
11.17 | PROVISIÓN Y COLOCACIÓN DE VALVULA DE RETENCION DN (21/2") PARA TANQUE TIPO COPA | un. | 1,00 |
11.18 | PROVISIÓN Y COLOCACIÓN DE Reservorio Enterrado Cap.= 2.250 Lts. Dim.= 1.50mx1.50x1.00m (h. útil). | un. | 1,00 |
11.19 | PROVISIÓN Y COLOCACIÓN DE Bomba Centrifuga incluye bases Q= 200 Lts./min; Hman= 24 m.c.a., P= 2 HP Incluye Tablero de Comando y boyas de automatizacion en Tanque elevado PARA RESERVORIO | un. | 2,00 |
11.20 | PROVISIÓN Y COLOCACIÓN DE Llaves, Válvulas y Accesorios Reservorio | un. | 1,00 |
12 | DESAGUE CLOACAL | - | |
12.1 | PROVISION Y COLOCACION DE TUBO PVC SOLDABLE DN (40mm) | ml | 70,00 |
12.2 | PROVISION Y COLOCACION DE TUBO PVC SOLDABLE DN (50mm) | ml | 155,00 |
12.3 | PROVISION Y COLOCACION DE TUBO PVC SOLDABLE DN (75mm) | ml | 35,00 |
12.4 | PROVISION Y COLOCACION DE TUBO PVC SOLDABLE DN (100mm) | ml | 95,00 |
12.5 | PROVISION Y COLOCACION DE TUBO PVC SOLDABLE DN (150mm) | ml | 55,00 |
12.6 | PROVISION Y COLOCACION DE Accesorios de PVC rigidos (codos, te, ramalas, reducciones, anillo de gomas ) | gl. | 1,00 |
12.7 | PROVISION Y COLOCACION DE REJILLA DE PISO SIFONADA 150x150x50 | un. | 24,00 |
12.8 | PROVISION Y COLOCACION DE REJILLA DE PISO SIFONADA 100x100x50 | un. | 18,00 |
12.9 | PROVISION Y COLOCACION DE REGISTRO CLOACAL 40x40 | un. | 6,00 |
12.10 | PROVISION Y COLOCACION DE REGISTRO CLOACAL 60x60 | un. | 5,00 |
12.11 | PROVISION Y COLOCACION DE CAMARA SEPTICA 1 | gl. | 1,00 |
12.12 | PROVISION Y COLOCACION DE CAMARA SEPTICA 2 | gl. | 2,00 |
12.13 | PROVISION Y COLOCACION DE POZO CIEGO 1 | gl. | 1,00 |
12.14 | PROVISION Y COLOCACION DE POZO CIEGO 2 | gl. | 2,00 |
13 | DESAGUE PLUVIAL | - | |
13.1 | PROVISION Y COLOCACION DE TUBO PVC SOLDABLE DN (200mm) | ml | 154,00 |
13.2 | PROVISION Y COLOCACION DE PLATO PLUVIAL DE ACERO GALVANIZADO: PLATO PLUVIAL TIPO EMBUDO PARA 3 BAJADAS PLUVIALES DE 200mm | un. | 2,00 |
13.3 | PROVISION Y COLOCACION DE CODOS, TEES, REDUCCIONES, RAMALES, REJILLAS DE INFILTRACION, ETC PARA EL SISTEMA EN SU CONJUNTO. | gl. | 1,00 |
13.4 | PROVISION Y COLOCACION DE REJILLAS: CANAL PLUVIAL CON REJILLA LINEAL 40X40 | ml | 26,00 |
13.5 | PROVISION Y COLOCACION DE REJILLAS: CANAL PLUVIAL CON REJILLA LINEAL 30X30 | ml | 75,00 |
13.6 | PROVISION Y COLOCACION DE CANALETAS METALICAS: CANALETA PLUVIAL | ml | 133,00 |
14 | PCI | - | |
14.1 | Boca de Incendio Equipada - BIE | un. | 17,00 |
14.2 | Boca de Incendio Siamesa - BIS Con Valvula de Retencion | un. | 1,00 |
14.3 | Extintor de Polvo Químico-EI ABC 6Kg | un. | 63,00 |
14.4 | Extintor de CO2- 6kg | un. | 2,00 |
14.5 | Valde de Arena Fina | un. | 8,00 |
14.6 | Alarma acústica y visual - AAV | un. | 22,00 |
14.7 | Pulsador manual de control - PMS | un. | 22,00 |
14.8 | Detector de humo y calor - DHC | un. | 126,00 |
14.9 | Detector Termovelocimétrico - DTV | un. | 14,00 |
14.10 | Detector de Haz de Luz | un. | 3,00 |
14.11 | Iluminación de emergencia (20 W) (1 Foco) - IE 1 | un. | 107,00 |
14.12 | Señalización de Emergencia | un. | 75,00 |
15 | PANEL CENTRAL + INSTALACION ELECTRICA | - | |
15.1 | Panel de Control Central | un. | 1,00 |
16 | INSTALACION HIDRÁULICA | - | |
16.1 | Provisión y colocación de accesorios (tees, codos, uniones, etc)Tubos de A°G° diametro según planos para distribucion, incluye accesorio para su instalacion y puesta en funcionamiento | gl. | 1,00 |
16.2 | Bomba Centrífuga-Con Tableros y automatizaciones Q=1000 Lts./min; Hm= 64 m.c.a.; P= 30 HP Con base Metalica | un. | 1,00 |
16.3 | Bomba Hidroneumática Tanque= 60 Lts.; Q= 15 Lts./min Tanque= 60 Lts.; Q= 15 Lts./min Hm=65 m.c.a.; P= 1.0 Hp Con Tableros | un. | 1,00 |
16.4 | Tubos de A°G° diametro según planos para distribucion, incluye accesorio para su instalacion y puesta en funcionamiento | un. | 1,00 |
16.5 | KIT COMPLETO INODORO CISTERNA BAJA | un. | 30,00 |
16.6 | MINGITORIO BLANCO C/SIFON | un. | 16,00 |
16.7 | BACHA LAVATORIO SOBREPONER | un. | 26,00 |
16.8 | Griferia MONOCOMANDO LAVATORIO | un. | 22,00 |
16.9 | Griferia CROMADA PARA MINGITORIO | un. | 16,00 |
16.10 | CANILLA LAVATORIO AUTOMATICA | un. | 4,00 |
16.11 | GRIFERIA MONOCOMANDO DUCHA | un. | 18,00 |
17 | INSTALACIONES ELECTRICAS: Alimentación a Tableros | - | |
17.1 | Acometida en media tension desde la red de ande con todo su equipamiento | gl. | 1,00 |
17.2 | Puesto de entrada y medicion | gl. | 1,00 |
17.3 | Provision y montaje de tablero general conforme esquema unifilar con juego de barras R.S.T.N y tierra, aisladores con todas las llaves termomagneticas, con instrumentos de medicion, correinte, tension y otros | gl. | 1,00 |
17.4 | Provision y montaje de tablero principal TPN, conforme esquema unifilar, con juego de barras y con todas las llaves termomagneticas incluidas | gl. | 1,00 |
17.5 | Montaje e instalacion del sistema de puesta a tierra del puesto de distribucion | gl. | 1,00 |
18 | INSTALACIONES ELECTRICAS: Tablero Seccional Normal (TGN) | - | |
18.1 | CAJA METALICA DE 800x1900x400mm | un. | 1,00 |
18.2 | DISYUNTOR TRIF. 630 AMP. 36 KA | un. | 1,00 |
18.3 | DISYUNTOR TRIF. 400 AMP. 36 KA | un. | 1,00 |
18.4 | DISYUNTOR TRIF. 160 AMP. 18 KA | un. | 1,00 |
18.5 | DISYUNTOR TRIF. 40 AMP. 06KA | un. | 2,00 |
18.6 | DISYUNTOR TRIF. 32 AMP. 06KA | un. | 1,00 |
18.7 | TRANSFORMADOR DE CORRIENTE 800/5 AMP. | un. | 4,00 |
18.8 | CENTRAL DE MEDIDA DIGITAL,DESCARGAD. TENSION BK20S-T2 1P 385V 40KA,SISTEMA DE DISTRIBUCION 630 AMP (FASES, NEUTRO Y TIERRA) | un. | 1,00 |
19 | INSTALACIONES ELECTRICAS: Tablero Seccional de Emergencia (TGE) | - | |
19.1 | CAJA METALICA DE 800x1900x400mm | un. | 1,00 |
19.2 | DISYUNTOR TRIF. 400 AMP. 36 KA | un. | 1,00 |
19.3 | DISYUNTOR TRIF. 125 AMP. 15 KA | un. | 2,00 |
19.4 | DISYUNTOR TRIF. 100 AMP. 15 KA | un. | 1,00 |
19.5 | DISYUNTOR TRIF. 63 AMP. 06KA | un. | 1,00 |
19.6 | DISYUNTOR TRIF. 32 AMP. 06KA | un. | 2,00 |
19.7 | DISYUNTOR TRIF. 25 AMP. 06KA | un. | 6,00 |
19.8 | DISYUNTOR TRIF. 25 AMP. 06KA | un. | 6,00 |
19.9 | DISYUNTOR TRIF. 25 AMP. 06KA | un. | 2,00 |
19.10 | DISYUNTOR UNIP. 16 AMP. 06 KA | un. | 25,00 |
19.11 | CONTACTOR UNIPOLAR 16 AMP. | un. | 16,00 |
19.12 | SISTEMA DE DISTRIBUCION 400 AMP (FASES, NEUTRO Y TIERRA)DESCARGADOR 45KA | un. | 1,00 |
20 | INSTALACIONES ELECTRICAS: Tablero Seccional de Planta Baja 1 (TS-PB-1) | - | |
20.1 | CAJA METALICA DE 36 MODULOS + LIM. | un. | 1,00 |
20.2 | DISYUNTOR TRIF. 40 AMP. 06KA | un. | 1,00 |
20.3 | DISYUNTOR UNIP. 25 AMP. 06 KA | un. | 2,00 |
20.4 | DISYUNTOR UNIP. 16 AMP. 06 KA | un. | 10,00 |
20.5 | SISTEMA DE DISTRIBUCION 40 AMP (FASES, NEUTRO Y TIERRA)INTERRUPTOR DIFERENCIAL 4x25A-30ms | un. | 1,00 |
21 | INSTALACIONES ELECTRICAS: Tablero Seccional de Planta Baja 2 y TCL (TS-PB-2)(TCL) | - | |
21.1 | CAJA METALICA DE 80 MODULOS + LIM. | un. | 1,00 |
21.2 | CAJA METALICA DE 24 MODULOS (TCL) | un. | 1,00 |
21.3 | DISYUNTOR TRIF. 125 AMP. 15KA | un. | 1,00 |
21.4 | DISYUNTOR UNIP. 16 AMP. 06 KA | un. | 47,00 |
21.5 | SISTEMA DE DISTRIBUCION 125 AMP (FASES, NEUTRO Y TIERRA)INTERRUPTOR DIFERENCIAL 4x25A-30ms,INTERRUPTOR DIFERENCIAL 2x25A-30ms | un. | 1,00 |
22 | INSTALACIONES ELECTRICAS: Tablero Seccional de Planta Baja 3 (TS-PB-3) | - | |
22.1 | CAJA METALICA DE 36 MODULOS + LIM. | un. | 1,00 |
22.2 | DISYUNTOR TRIF. 40 AMP. 06KA | un. | 1,00 |
22.3 | DISYUNTOR UNIP. 16 AMP. 06 KA | un. | 12,00 |
22.4 | SISTEMA DE DISTRIBUCION 40 AMP (FASES, NEUTRO Y TIERRA)INTERRUPTOR DIFERENCIAL 4x25A-30ms | un. | 1,00 |
23 | INSTALACIONES ELECTRICAS: Tablero Seccional de Planta Primer Piso (TS-1P) | - | |
23.1 | CAJA METALICA DE 36 MODULOS + LIM. | un. | 1,00 |
23.2 | DISYUNTOR TRIF. 50 AMP. 06KA | un. | 1,00 |
23.3 | DISYUNTOR TRIF. 25 AMP. 06KA | un. | 2,00 |
23.4 | DISYUNTOR UNIP. 16 AMP. 06 KA | un. | 13,00 |
23.5 | SISTEMA DE DISTRIBUCION 50 AMP (FASES, NEUTRO Y TIERRA)INTERRUPTOR DIFERENCIAL 4x25A-30ms | un. | 1,00 |
24 | INSTALACIONES ELECTRICAS: Tablero Seccional Cantina (TS-CA) | - | |
24.1 | CAJA METALICA DE 36 MODULOS + LIM. | un. | 1,00 |
24.2 | DISYUNTOR TRIF. 32 AMP. 06KA | un. | 1,00 |
24.3 | DISYUNTOR TRIF. 25 AMP. 06KA | un. | 1,00 |
24.4 | DISYUNTOR UNIP. 16 AMP. 06 KA | un. | 8,00 |
24.5 | SISTEMA DE DISTRIBUCION 32 AMP (FASES, NEUTRO Y TIERRA)INTERRUPTOR DIFERENCIAL 4x25A-30ms,INTERRUPTOR DIFERENCIAL 2x25A-30ms | un. | 1,00 |
25 | INSTALACIONES ELECTRICAS: Tablero Seccional Planta Tercer Piso (TS-3P) | - | |
25.1 | CAJA METALICA DE 1200X600X150MM | un. | 1,00 |
25.2 | DISYUNTOR TRIF. 100 AMP. 15KA | un. | 1,00 |
25.3 | DISYUNTOR TRIF. 25 AMP. 06KA | un. | 4,00 |
25.4 | DISYUNTOR UNIP. 25 AMP. 06 KA | un. | 2,00 |
25.5 | DISYUNTOR UNIP. 16 AMP. 06 KA | un. | 35,00 |
25.6 | CONTACTOR UNIPOLAR 16 AMP. | un. | 12,00 |
25.7 | SISTEMA DE DISTRIBUCION 100 AMP (FASES, NEUTRO Y TIERRA)INTERRUPTOR DIFERENCIAL 4x25A-30ms | un. | 11,00 |
26 | INSTALACIONES ELECTRICAS: Tablero Seccional Bomba de Agua (TSBA) | - | |
26.1 | CAJA METALICA DE 500x500x150mm | un. | 1,00 |
26.2 | SISTEMA DE DISTRIBUCION 25 AMP (FASES, NEUTRO Y TIERRA)DISYUNTOR TRIF. 25 AMP. 06KA,DISYUNTOR TRIF. 20 AMP. 06KA | un. | 1,00 |
27 | INSTALACIONES ELECTRICAS: Tablero Seccional Bomba de Incendio (TSBI) | - | |
27.1 | CAJA METALICA DE 500x500x150mm | un. | 1,00 |
27.2 | SISTEMA DE DISTRIBUCION 125 AMP (FASES, NEUTRO Y TIERRA)DISYUNTOR TRIF. 20 AMP. 06KA,DISYUNTOR TRIF. 125 AMP. 15 KA | un. | 1,00 |
27.3 | Tablerode mando con todo sus accesorios, conexiones al motor y con el tablero de fuerza | gl. | 1,00 |
28 | INSTALACIONES ELECTRICAS: Alimentación a circuitos | - | |
28.1 | Mano de obra- materiales menores, incluido todos los accesorios de conexión, cables unifilares, codos, adaptadores y montaje puestas en funcionanmiento | gl. | 1,00 |
29 | INSTALACIONES ELECTRICAS: Bandejas p/ circuitos eléctricos | - | |
29.1 | Mano de obra- materiales menores, incluido todos los accesorios de conexión y montaje puestas en funcionanmiento | gl. | 1,00 |
30 | INSTALACIONES ELECTRICAS: Sistema de puesta a tierra de Servicios y Pararrayos | - | |
30.1 | PARARRAYOS DESIONIZANTE R=100 mts | un. | 1,00 |
30.2 | MASTIL PARA PARARRAYOS | un. | 1,00 |
30.3 | JABALINA DE CU 5/8"X2,4MM | un. | 6,00 |
30.4 | CABLE CU DESNUDO 1x16 mm² p/ Recorrido de Bandejas,CABLE CU DESNUDO 1x70 mm²,CABLE CU DESNUDO 1x95 mm², | ml | 579,00 |
30.5 | CABLE CU DESNUDO 1x50 mm² | ml | 55,00 |
30.6 | EXCAVACION DE ZANJAS | ml | 50,00 |
30.7 | BARRA DE COBRE 60x10 mm | ml | 0,30 |
30.8 | CAÑO METALICO 1"AISLADOR CON SOPORTE PARA CABLE DE BAJADA | ml | 20,00 |
31 | INSTALACIONES ELECTRICAS: Mecanismos y tomas | - | |
31.1 | INTERRUPTOR UNIPOLAR | un. | 41,00 |
31.2 | INTERRUPTOR BIPOLAR | un. | 18,00 |
31.3 | TOMA UNIVERSAL C/ TIERRA | un. | 88,00 |
31.4 | TOMA P/ COMPUTADORA | un. | 24,00 |
31.5 | TOMA SCHUKO | un. | 18,00 |
32 | INSTALACIONES ELECTRICAS: Bandejas y Ductos p/ Señales | - | |
32.1 | BANDEJA PORTACABLES PERF 150X50MM TIRA 3M | un. | 70,00 |
32.2 | Tablero metalico para llaves TM, con barra, fase, neutro y tierra doble puerta, con lus piloto de tension, UPS | un. | 1,00 |
32.3 | Caja de destribucion para electroducto | un. | 140,00 |
32.4 | Bandeja regilladas varilla galvanizada | ml | 150,00 |
33 | INSTALACIONES ELECTRICAS: Puesto de entrega y distribucion (estimado) | - | |
33.1 | POSTE DE HORMIGÓN ARMADO 12/200 KGF | un. | 2,00 |
33.2 | POSTE DE HORMIGÓN ARMADO 12/300 a 500 KGF | un. | 1,00 |
33.3 | CIMENTACION DE POSTES | m3 | 1,00 |
33.4 | Ampliacion de red Media Tension materiales de fijacion y conexión | gl. | 1,00 |
33.5 | Acometida media Tension seccionadores fus. Aereo | un. | 15,00 |
33.6 | Acometida media Tension terminales para cables aislado | un. | 19,00 |
33.7 | DESCARGADOR MT | un. | 3,00 |
34 | INSTALACIONES ELECTRICAS: REGISTROS | - | |
34.1 | REGISTRO DE MAMPOSTERÍA 60X60X60CM (ELECTRICO) | un. | 2,00 |
34.2 | REGISTRO DE MAMPOSTERÍA 40X40X60CM (SEÑALES) | un. | 2,00 |
35 | INSTALACIONES ELECTRICAS: Artefactos de iluminación electrica | - | |
35.1 | PH ARTEF LED ESTANCO ADO 33W 3600LM | un. | 76,00 |
35.2 | PANEL LED EMB CUAD 40W 4000LM | un. | 157,00 |
35.3 | SOPORTE P/ ADOSAR PANEL LED 605x605 TIPO CAJA | un. | 157,00 |
35.4 | ARTEF ADO TECHO GX53 C/LAMP LED 10W 2700/4000K CIRC NEGRO | un. | 62,00 |
35.5 | APLIQUE ADO PARED 1L R7S C/ LAMP LED 3,2W | un. | 6,00 |
35.6 | PH ARTEF LED COMERCIAL 14W 1200LM 3000K | un. | 39,00 |
35.7 | PH CONECTOR PARA CONEXIÓN BATTEN | un. | 39,00 |
35.8 | ARTEF ADO TECHO DICRO GU10 C/LAMP LED 6W 2700/4000K CIRC NEGRO | un. | 84,00 |
35.9 | PH PROYECTOR LED 100W 10500LM 4000K EXT ESSENTIAL | un. | 26,00 |
35.10 | PH PROYECTOR LED 30W 3000K EXT ESSENTIAL | un. | 6,00 |
35.11 | PH ALUMBRADO PUBLICO LED 67W 9300LM 4000K | un. | 13,00 |
35.12 | BRAZO PARA ALUMBRADO PUBLICO 2 PULG x 1,50 MTS GALVANIZADO | un. | 13,00 |
35.13 | PH ARTEF LED INDUST 115W 15500LM | un. | 34,00 |
35.14 | PH ARTEF LED INDUST 192W 26500LM | un. | 50,00 |
35.15 | FAROLA 1L C/ LAMP LED E27 50W 3000K NEGRO | un. | 9,00 |
35.16 | PEDESTAL PARA FAROLA 2,5" h=250cm NEGRO | un. | 9,00 |
35.17 | PROVISION DE TRANSFORMADOR PEDESTAL 300KVA | un. | 1,00 |
35.18 | PROVISION DE GENERADOR 275 KVA CABINADO CON TABLERO DE POTENCIA | un. | 1,00 |
35.19 | Uso de elevador para montaje de artefactos | gl. | 1,00 |
36 | ABERTURAS DE MADERAS | ||
36.1 | Puerta madera eucalipto doble hoja de 1,60 x 2,10 placa ilustrada con marco contra marco, cerradura yale y manijon de 0,30 colocado | un. | 14,00 |
36.2 | Puerta madera eucalipto una hoja de 0,80 x 2,10 placa ilustrada con marco, cerradura yale colocado | un. | 27,00 |
37 | CARPINTERIA METÁLICA | ||
37.1 | Puerta metalica de 1,60 x 2,10 doble hoja | un. | 7,00 |
37.2 | Puerta metalica de 3,00 x 2,50 doble hoja | un. | 2,00 |
37.3 | Baranda metálica 1,10 | ml | 200,00 |
37.4 | Pasamano metálico | ml | 20,00 |
38 | VIDRIOS | ||
38.1 | Ventanas tipo maximo aire Linea Gold Fachada Laterales 10,63 x 1,30 | un. | 8,00 |
38.2 | Ventanas tipo maximo aire Linea Gold Fachada frontal 8,40 x 1,30 | un. | 3,00 |
38.3 | Ventanas tipo maximo aire Linea Gold Fachada frontal 23 x 1,30 | un. | 1,00 |
38.4 | Fachada tipo muro cortina con columnas verticales de 150mm - 750 m2 aproximadamente | un. | 1,00 |
39 | Espejos | - | |
39.1 | Espejos 4mm pulidos | m2 | 22,00 |
40 | COLOCACION DE MAMPARAS DE PVC | ||
40.1 | Mamparas de baños con estructura en chapa galvanizada y revestimiento en PVC 71 x 200 | m2 | 142,00 |
40.2 | Accesorio puertas baños | un. | 42,00 |
41 | SERVICIO DE PINTURA | ||
41.1 | De paredes interiores al agua con enduído | m2 | 620,00 |
41.2 | De paredes exteriores | m2 | 2.091,60 |
41.3 | De pilares | ml | 371,84 |
41.4 | De cielorrasos y graderias al látex | m2 | 7.632,00 |
41.5 | Pintura de canchas exteriores | m2 | 1.315,00 |
41.6 | Pintura de lineas de cancha exterior/interior | ml | 1.010,85 |
41.7 | De aberturas de maderas con esmalte | m2 | 80,64 |
41.8 | De baranda metálica | ml | 20,00 |
41.9 | De pasamano metálico | ml | 200,00 |
41.10 | REVESTIMIENTO EPOXICO + PINTURA URETANO (cancha interior) | m2 | 700,00 |
41.11 | MASILLA PARA JUNTAS | un. | 1,00 |
41.12 | Pintura Epóxica con base Poliuretánica para pintar la cancha y la superficie al contorno de la cancha (exterior) |
m2 | 515,00 |
41.13 | Pintura Epóxica con base Poliuretánica para pintar la cancha y la superficie al contorno de la cancha (exterior) |
m2 | 800,00 |
42 | SEÑALIZACION | ||
42.1 | Letras corpóreas cuerpo de acm con tapa de acrilico e iluminación led para Rohayhu 3,81 x 1,47 | gl. | 1,00 |
42.2 | Letras corpóreas cuerpo de acm con tapa de acrilico e iluminación led para Villa 4,48 x 2,23 | gl. | 1,00 |
42.3 | Letras corpóreas cuerpo de acm con tapa de acrilico e iluminación led para Elisa 5,11 x 2,36 | gl. | 1,00 |
42.4 | Letras corpóreas cuerpo de acm con tapa de acrilico e iluminación led para Corazón 2,32 x 2,64 | gl. | 1,00 |
42.5 | Letras corpóreas cuerpo de acm con tapa de acrilico e iluminación led para Estanislao Frutos 12,00 x 0,79 | gl. | 1,00 |
42.6 | Letras corpóreas cuerpo de acm con tapa de acrilico e iluminación led para polideportivo 6,00 x 0,79 | gl. | 1,00 |
42.7 | Letras corpóreas cuerpo de acm con tapa de acrilico e iluminación led para Villa Elisa 4,00 x 0,60 | gl. | 1,00 |
43 | SERVICIO DE PROVISION / MONTAJE DE EQUIPOS/ JUEGOS DE PARQUES/PLAZAS | ||
43.1 | Arcos de 3x2m para futbol de Salon y futbol 5 con red incluida | un. | 4,00 |
43.2 | Aro - Gold Portable Tamaño - 54" x 32" (137.2 cm x 81.3 cm) |
un. | 2,00 |
43.3 | Aro con soporte de caño metalico de 8mm fijo (exterior) | un. | 2,00 |
43.4 | Butacas plasticas para palco vip con respaldero | un. | 50,00 |
43.5 | Butacas con base metalica suplentes para 9 personas | un. | 3,00 |
43.6 | Parque de plástica 1 torre + Hamaca. con 2 asientos normales de plastico - Madera Plástica. | un. | 1,00 |
43.7 | Calesita metalica para niños de 4x4m | un. | 1,00 |
43.8 | Banco de plaza con pie de hierro | un. | 6,00 |
43.9 | Casillero metalico de 06 (Seis) Compartimientos (vestuario arbitros damas y caballeros) | un. | 2,00 |
43.10 | Casillero de 08 (Ocho) Compartimientos, (vestuarios Damas y caballeros) | un. | 8,00 |
43.11 | Pasto cabayu | m2 | 791,00 |
OBSERVACIÓN
EN BASE A LAS NORMAS A LA CUALES SE DEBEN REGIR LAS INSTALACIONES SANITARIAS SON LAS SIGUIENTES:
ITEM 11. Provisión y Colocación de Tuberías: para instalación se cumplirá con lo establecido en la NORMA PARAGUAYA INTN NP 68. Las Tuberías y accesorios a ser instalados serán de Polipropileno Termo fusión PN 20. Los tubos soportan una presión máxima de 16,0 kg/cm2. Las tuberías se verán reforzadas por uniones simples cada 12 m y uniones dobles cada 18 m. Este presupuesto incluye provisión y colocación de las tuberías con todos sus accesorios, los soportes correspondientes en las tuberías aéreas conforme lo establecen las especificaciones técnicas con una separación no menor a 1,5 m y las pruebas hidráulicas correspondientes. Las tuberías y accesorios son fabricados según normas DIN 8077/78, 16962 y 16962 e IRAM 13470/13471.
ITEM 12- DESAGUE CLOACAL
Las tuberías de PPR mencionadas deben ser para altas temperaturas. Las tuberías de PVC deben ser las de Alta densidad
Asimismo, se adjunta en el SICP el documento por el cual se establecen las especificaciones técnicas de la obra. Dicho documento forma parte integral del Pliego de Bases y Condiciones del presente proceso licitatorio. VER DOCUMENTO ADJUNTO EN EL SICP en la pestaña "ESPECIFICACIONES TÉCNICAS".
Estas Normas Paraguayas de Accesibilidad al Medio Físico fueron elaboradas por la CTN 45 “ACCESIBILIDAD – Subcomité Accesibilidad al Medio Físico”, y aprobadas por el Instituto Nacional de Tecnología, Normalización y Metrología (INTN). Se encuentran publicadas en el Portal de Contrataciones Públicas (www.contrataciones.gov.py), vínculo “Marco Legal/Documentos de Interés”, desde donde podrán ser descargadas.
Las normas de accesibilidad que serán aplicadas deben incluirse en la Lista de Cantidades (Cómputo métrico) del Formulario de Oferta para permitir su cotización en conjunto con las obras objeto del contrato.
En el marco de la política de Compras Públicas Sustentables, cuyo fundamento radica en la consideración de prevalencia del impacto ambiental y social al momento de llevar adelante una contratación pública, las Contratantes deberán establecer la inclusión de las Normas Técnicas en las Contrataciones que tengan por objeto una obra nueva (Ej.: construcción de edificios, hospitales, escuelas, plazas, calles, y todas las obras que comprendan espacios de uso público, etc.)
En las contrataciones de servicios de reparación y mantenimiento de edificios, así como en la restauración de edificios históricos podrán aplicarse las Normas de Accesibilidad en la medida que razonablemente puedan ser admitidas.
El cumplimiento de estas normas en la ejecución de los trabajos deberá ser exigido a las Contratistas, y para el efecto, se tomarán como referencia a las Normas de Accesibilidad de las Personas al Medio Físico elaboradas por el Comité Técnico de Normalización CTN 45 “Accesibilidad”, del Instituto Nacional de Tecnología, Normalización y Metrología (INTN).
La obra debe ser ejecutada por el contratista principal y los subcontratistas en su caso, teniendo en cuenta la legislación vigente en materia ambiental, y las evaluaciones, licencias, autorizaciones, permisos, según corresponda, con el fin de que la misma cause impacto negativo mínimo directo o indirecto al medio ambiente.
Se entiende por impacto negativo todo el conjunto de alteraciones directas e indirectas provocadas por las actividades humanas sobre el medio físico, biótico, socio-económico, cultural, histórico y antropológico y que resulten costos sociales para el Estado y una disminución de la calidad de vida de la población en la que se va a ejecutar la obra.
Descripción |
N O A P L I C A
|
|
Para la presente contratación se pone a disposición los siguientes planos o diseños:
Lista de Planos o Diseños |
||
Plano o Diseño N° |
Nombre del Plano o Diseño |
Propósito |
|
VER DOCUMENTO ADJUNTO |
|
Los planos de la obra con la respectiva aprobación municipal se encuentran publicados en el SICP junto con el expediente del llamado.
Se entregará al contratista en forma gratuita, un (1) ejemplar de los planos que a su vez será publicado en el SICP con la convocatoria de la contratación. El contratista se encargará de obtener, por su cuenta, todos los demás ejemplares que pudiese necesitar. El contratista no podrá utilizar para otros fines distintos a los del contrato, ni comunicar a terceros los planos, especificaciones y demás documentos presentados por la contratante, excepto si ello se considera estrictamente necesario para la ejecución del contrato.
La contratante es responsable por la obtención y entrega de los planos al contratista antes de la expedición de la orden de inicio de los trabajos, conforme a las disposiciones municipales vigentes y toda otra aprobación necesaria para el inicio de la ejecución de las obras.
El atraso de parte de la contratante en la entrega de los planos prorrogará en igual forma el inicio de la ejecución de las obras.
La obra a ser realizada será conforme a lo siguiente:
SE RELIZARÁ EN PLAZA AMERICA ubicado en la calle NTRA SEÑORA C/ ACAHAY
El plazo de ejecución será de 180 días desde la orden de inicio. La orden de inicio se dará dentro de 6 días luego de la suscripción del contrato.
El Contratista está obligado a habilitar un libro de obras foliado y rubricado por la Administración Municipal, en ella deberá registrar desde el primer día todos los pormenores referentes a la ejecución de las obras objeto del Contrato.
Las obras contratadas que requieran de la obtención de requisitos de carácter ambiental, no podrán iniciarse antes de la obtención y presentación a la contratante de dichos requisitos.
Las empresas contratistas encargadas de la construcción de obras de infraestructura y/o viales tendrán la obligación de exhibir gráficamente letreros o vallas en lugares visibles que identifiquen a la obra y deberá contener mínimamente cuanto sigue:
El código QR mencionado en la presente cláusula, es generado a través del SICP con la emisión del código de contratación, permitiendo que a través de aplicaciones móviles pueda ser corroborada la información disponible del contrato y la situación contractual del mismo.
La convocante puede incluir otros requisitos adicionales, como por ejemplo:
- EL Oferente deberá incluir en su oferta una descripción preliminar del método de trabajo y cronogramas específicos, incluyendo gráficos y diseños. El Cronograma de actividades deberá ser elaborado en base al diagrama de Grantt con el desarrollo de todos los ítems de trabajo, en el cual se indique la fecha de inicio, duración, porcentaje de ejecución previsto para cada mes y la fecha de terminación de los trabajo. Es obligación del Oferente cumplir con el cronograma una vez adjudicado, el cual será estrictamente fiscalizado por la Contratante.
-EL Oferente deberá incluir en su oferta física, la Planilla de lista de precios ofertados de los ítems y sub ítems en formato digital Excel editable, grabado en un medio magnético (CD, DVD o PENDRIVE).
- EL Oferente deberá incluir en su oferta física, el Certificado de Visita al sitio de obra, debidamente firmada por el responsable designado por la Convocante
El documento requerido para acreditar el cumplimiento contractual, será:
El documento requerido para acreditar el cumplimiento contractual, será: Certificado de Obras mensual/final.
Serán presentados 6 (seis) certificados
Frecuencia: mensual.
Planificación de indicadores de cumplimiento:
INDICADOR |
TIPO |
FECHA DE PRESENTACIÓN PREVISTA |
Certificado 1 |
Certificado de Obra |
Junio 2022 |
Certificado 2 |
Certificado de Obra |
Julio 2022 |
Certificado 3 |
Certificado de Obra |
Agosto 2022 |
Certificado 4 |
Certificado de Obra |
Septiembre 2022 |
Certificado 5 |
Certificado de Obra |
Octubre 2022 |
Certificado 6 |
Certificado de Obra |
Noviembre 2022 |
De manera a establecer indicadores de cumplimiento, a través del sistema de seguimiento de contratos, la convocante deberá determinar el tipo de documento que acredite el efectivo cumplimiento de la ejecución del contrato, así como planificar la cantidad de indicadores que deberán ser presentados durante la ejecución. Por lo tanto, la convocante en este apartado y de acuerdo al tipo de contratación de que se trate, deberá indicar el documento a ser comunicado a través del módulo de Seguimiento de Contratos y la cantidad de los mismos.
La convocante adjudicará el contrato al oferente cuya oferta haya sido evaluada como la más baja y cumpla sustancialmente con los requisitos de las bases y condiciones, siempre y cuando la convocante determine que el oferente está calificado para ejecutar el contrato satisfactoriamente.
1. La adjudicación en los procesos de contratación en los cuales se aplique la modalidad de contrato abierto, se efectuará por las cantidades o montos máximos solicitados en el llamado, sin que ello implique obligación de la convocante de requerir la provisión de esa cantidad o monto durante de la vigencia del contrato, obligándose sí respecto de las cantidades o montos mínimos establecidos.
2. En caso de que la convocante no haya adquirido la cantidad o monto mínimo establecido, deberá consultar al proveedor si desea ampliarlo para el siguiente ejercicio fiscal, hasta cumplir el mínimo.
3. Al momento de adjudicar el contrato, la convocante se reserva el derecho a disminuir la cantidad requerida, por razones de disponibilidad presupuestaria u otras razones debidamente justificadas. Estas variaciones no podrán alterar los precios unitarios u otros términos y condiciones de la oferta y de los documentos de la licitación.
En aquellos llamados en los cuales se aplique la modalidad de contrato abierto, cuando la Convocante deba disminuir cantidades o montos a ser adjudicados, no podrá modificar el monto o las cantidades mínimas establecidas en las bases de la contratación.
La comunicación de la adjudicación a los oferentes será como sigue:
1. Dentro de los cinco (5) días corridos de haberse resuelto la adjudicación, la convocante comunicará a través del Sistema de Información de Contrataciones Públicas, copia del informe de evaluación y del acto administrativo de adjudicación, los cuales serán puestos a disposición pública en el referido sistema. Adicionalmente el sistema generará una notificación a los oferentes por los medios remotos de comunicación electrónica pertinentes, la cual será reglamentada por la DNCP.
2. En sustitución de la notificación a través del Sistema de Información de Contrataciones Públicas, las convocantes podrán dar a conocer la adjudicación por cédula de notificación a cada uno de los oferentes, acompañados de la copia íntegra del acto administrativo y del informe de evaluación. La no entrega del informe en ocasión de la notificación, suspende el plazo para formular protestas hasta tanto la convocante haga entrega de dicha copia al oferente solicitante.
3. En caso de la convocante opte por la notificación física a los oferentes participantes, deberá realizarse únicamente con el acuse de recibo y en el mismo con expresa mención de haber recibido el informe de evaluación y la resolución de adjudicación.
4. Las cancelaciones o declaraciones desiertas deberán ser notificadas a todos los oferentes, según el procedimiento indicado precedentemente.
5. Las notificaciones realizadas en virtud al contrato, deberán ser por escrito y dirigirse a la dirección indicada en el contrato.
Una vez notificado el resultado del proceso, el oferente tendrá la facultad de solicitar una audiencia a fin de que la convocante explique los fundamentos que motivan su decisión.
La solicitud de audiencia informativa no suspenderá ni interrumpirá el plazo para la interposición de protestas.
La misma deberá ser solicitada dentro de los dos (2) días hábiles siguientes en que el oferente haya tomado conocimiento de los términos del Informe de Evaluación de Ofertas.
La convocante deberá dar respuesta a dicha solicitud dentro de los dos (2) días hábiles de haberla recibido y realizar la audiencia en un plazo que no exceda de dos (2) días hábiles siguientes a la fecha de respuesta al oferente.
Luego de la notificación de adjudicación, el proveedor deberá presentar en el plazo establecido en las reglamentaciones vigentes, los documentos indicados en el presente apartado.
|
|
|
|
|
|
|
2. Documentos. Consorcios |
|
|
|
|